Project Description

2N Data Center complete with all new mechanical and electrical systems. Procurement and installation of (3) 400 ton water cooled chillers, (5) 100 HP chill water pumps, (4) 90,000CFM built up air handling units, (7) Leibert System III CRAC Units, (3) plate frame heat exchangers, (9) self contained air handling units. These systems are supported by 3,900’ of 16” welded carbon steel pipe and another 6,200’ of smaller bore schedule 40 6” – 12” welded carbon steel pipe.

Arch/Engr:           Nelson Nelco Architects  /Syska Hennessey Group
Project Value:      $6.2 Million
Sq Footage:           365,000
Duration:              9 Months