Project Description

New Data Center with Three 750 ton chillers with 20 Liebert down flow CRAC units Dual fed interior chilled water loop

We installed the fuel oil piping for the generator, including 2 big underground fuel tanks.

Owner:                 Experian Information Solutions Group
Arch/Engr:           Blum Consulting Engineers
Project Value:      $6.5 Million
Sq. Footage:         77,250
Duration:              14 Months